A) Project Detail/Scope:
Name of Project : Marsyangdi – Kathmandu 220 kV Transmission Line Project
Scope: Construction of 220kV Transmission Line from Tanahu, Markichowk to Kathmandu, Matatirtha and Construction of 220kV GIS Substation at Tanahu, Markichowk & 220kV AIS Substation at Kathmandu, Matatirtha.
B) Project Objectives and Goals:
The objective of the project is to Construct 220kV Transmission Line from Tanahu, Markichowk to Kathmandu, Matatirtha and Construct 220kV GIS Substation at Tanahu, Markichowk & 220kV AIS Substation at Kathmandu, Matatirtha so that the power from Marsyangdi basin can be transmitted to Kathmandu to fulfill the load demand.
C) Contract Packages:
Package 1: Marsyangdi-Kathmandu 220 kV Transmission Line (ICB - PMD - MKTLP - 072/073 – 02)
Scope: Design, Supply, Installation and Commissioning of Marsyangdi – Kathmandu 220kV Transmission Line
IFB Publication Date: 02 February, 2016
Contract Agreement Date: 30 June, 2016
Contract Completion Date: March, 2019
Cost of Contract: USD 12,480,187.55 and NPR 684,962,937.89
Major Activities:
Major materials for construction has been delivered to site and Construction of about 100 tower foundation and about 8 tower erection work completed and other works on process.
Package 2: Marsyangdi-Kathmandu 220 kV Transmission Line (ICB - PMD - MKTLP - 072/073 – 03)
Scope: Design, Supply, Installation and Commissioning of 220kV Air Insulated Substation (AIS) in Matatirtha, Kathmandu and Gas Insulated Substation (GIS) in Markichowk, Marsyangdi
IFB Publication Date: 20 May, 2016
Contract Agreement Date: 22 December, 2016
Contract Completion Date: June, 2019
Cost of Contract: USD 15,693,422.42 and NPR 551,562,110.04
Major Activities:
Drawings and design of Major materials for construction has been approved & in process of manufacturing and site leveling work at both site has been completed.
D) Progress:
a) Physical: 40.27%
b) Financial: 31.25%
E) Disbursement Target of the Year:
Nepal Government: 300,000,000
ADB : 1,150,000,000
F) Disbursement Amount of the Year:
USD 4,011,866.00 NPR 1,62,991,214.12
G) Hindrance of the Project:
H) Efforts to Mitigate Hindrance:
I) Budget for F/Y 2017/18
Nepal Government: 300,000,000
ADB : 1,150,000,000
J) Target of Expenses for F/Y 2017/18:
Nepal Government: 300,000,000
ADB : 1,150,000,000
K) Social and Environmental Activities including GESI and their impacts to society:
The social and environmental activities including GESI are conducted and monitored by ESSD department, NEA.
L) Land and Building Details:
220kV Substation:
Tanahu, Markichowk: 69 ropani land acquisition completed
Matatirtha, Kathmandu: 110 ropani land acquisition almost complete
220kV Transmission Line:
Gorkha District: 48 ropani land acquisition for 44 tower pads almost complete
Dhading District: 119 ropani land acquisition for 98 tower pads compensation distribution on process
Chitwan District: 2 bigha land acquisition for 21 tower pads notice published
Kathmandu District: 5.5 ropani land acquisition for 3 tower pads on process
Tanahu District: 4 ropani land acquisition for 2 tower pads on process
Building:
School building of 40 rooms was acquired at the stage of land acquisition process for 22okV Matatirtha substation where PMD office and other project office are located now.