Utility Scale Grid tied Solar PV Project

                                                                                                                                                                                                                                Report of :  1st  Quarter

A)   Project Detail/Scope:

Selection of Independent Power Producer (IPP) for Setting of Utility Scale Grid tied Solar PV Project.

Started from 2073/74 and expected to completed on 2074/75.

​B)   Project Objective and Goals: Operate and Maintain the Project as per the provisions of the PPA so as to provide the electricity to NEA at specified quoted tariff (the Tariff Charges) up to 30th June 2023 2022 A.D. from the RCOD and then NRs 6.60/kWh for the contract period of 25 years.

C)    Contract Packages:

       Package 1: Process of Approval of Bidding Documents.

      Awarded:

             Contract Detail:

Scope:  Selection of Independent Power Producer (IPP) for Setting of Utility Scale Grid tied Solar PV Project under VGF model.

IFB Publication Data:

Contract Agreement Date:

Contract Completion Date:

Cost of Contract:

Major Activities

D)    Progress:

a) Physical: 10%

b) Financial:0%

 

E)    Disbursement Target of the Year:11000000

F)     Disbursement Amount of the Year: 0

G)     Hinderance of the Project:

H)     Efforts to Mitigate Hinderance:

I)       Budget for F/Y 2074/2075:11000000

J)      Targets of expenses for F/Y 2074/75: 11000000

K)      Social and Environmental Activities including GESI and their impacts to society:  

L)       Land and Building Details: 