A)   Project Details/Scope:

Dana Substation: 100 MVA,  220/132/33 kv  (Annapurna RM-3,  Dana , Myagdi)

 

Dana-Kushma Transmission line:

     Location ;  Myagdi  (Dana)  to Parbat (Khurkot),

     Voltage: 220kv,

     Length:38km,

     Conductor: Twine Moose ACSR

Kushma Substation;-100 MVA, 220/132/33 kv ( Kushma M-2 Khurkot, Parbat)

 

Kushma-New Butwal Transmission line:

      Location: Parbat (Khurkot), Baglung, Syangja, Palpa, Rupandehi, Nawalparasi

      Length:  88km

     Conductor: Twin HTLS

 

New Butwal Substation: 100 MVA ,  220/132/33 kV

 

New Butwal-Bardaghat Transmission Line:

     Location: Badera  to Bardaghat for  Nawalparasi  district.

     Voltage:  220kv:

     Length:  20 km (approx)

     Conductor :  Bison

B)  project Objectives and Goals:

To evacuate the paper generated by hydropower plants constructed in Kaligandaki river basin.

C)Contract packages:

 

Package 1:

ICB-PMD-KGTCP-071/72-03  Dated:- 20 May 2016

Contract Details:- Procurement of plant for Design, supply, Installation and Commissioning  of Dana Kushma 220 kV Transmission Line and associated Substations.

    Scope:

 Dana Substation-100 MVA, 220/132/33 kv (Annapurna RM-3,  Dana , Myagdi)

 

Dana-Kushma Transmission line:

Location : Myagdi (Dana)  to Parbat (Khurkot), Voltage: 220 kV       

 Length: 38 km

Conductor: Twine Moose ACSR

 

       Kushma Substation:- 100 MVA, 220/132/33 kv ( Kushma M-2 Khurkot, Parbat)

       IFB Publication Date: 29 June 2015

       Contract Agreement Date: 30  May 2016

       Contract Complection Date: Nov 2018

       Cost of Contract: NRP Equivalent 2912212863.78

      Package 2:

Re:  ICB-PMD-KGTCP-072/73-04  Dated-5 Dec 2017

Contract Details: Procurement of plant for Design, supply, Installation and Commissioning  of Kushma new Butwal  220 kV Transmission Line.

 

     Scope:

Kushma-New Butwal Transmission line

 Location; Parbat (Khurkot), Baglung, Syangja, Palpa, Rupandehi, Nawalparasi ;

 Length: 88km;

 Conductor: Twin HTLS;

       IFB Publication Date: 18 July 2016

       Contract Agreement Date: 5 Dec 2017

       Contract Complection Date: 1080 days from the effective date.

      Cost of Contract: USD  23,999,428.36 and NRP 659,651,003

 

  Package 3:

 ICB-PMD-KGTCP-073/74-03  Dated-5 Dec 2017

Contract Details: Procurement of plant for Design, supply, Installation and Commissioning  of New  Butwal Substation.  

    Scope:

New Butwal Substation- 100 MVA , 220/132/33 kv

 Location- Sunawal 12 Badera nawalparasi

       IFB Publication Date: 27 Feb 2017

       Contract Agreement Date: 8 Nov 2017

       Contract Completion Date:  June 18 2019

      Cost of Contract: USD 6,208,840.23 and NRP 364,209,838.1

 

Package 4:

 ICB-PMD-KGTCP-073/74-02 

Tender  Details: Procurement of plant for Design, supply, Installation and Commissioning  of New Butwal Bardaghat 220 kV Transmission Line.  

 

    Scope:

New Butwal-Bardaghat Transmission Line:

Location:  Badera nawalparasi to Bardaghat Nawalparasi

Voltage: 220kv

Length: 20 km (approx)  Conductor : Bison

       IFB Publication Date: 09 May 2017

      Is in Tender process.

D)  Progress:

  1. Physical : 26.07 %
  2. Financial: 19.94 %

E)  Disbursement  Target of the year :

F)  Disbursement  Amount of the year :

G)   Hinderance of the Projects :

RoW  issue in Pokhareabagar Myagdi and Majhaphat Parbat for Dana Kushma Section.

H)   Efforts to mitigate Hindrance:

a)      Frequent discussion and meeting with local people

b)      Social awareness Program

c)       Trainings for Local People

Local support program through CSR

 

I)   Budget for  f/y  2074/74

 Nepal Government – 170,000,000

ADB- 2,130,000,000

 

J)Target of expenses for F/Y 2017/18:

K)    Social and Environmental Activities including GESI their impacts to Socity:

 

a)      Public  hearing

b)      EHS implementation

c)       Plan for Plantaion

d)      Social awareness

e)      wildlife conservation training

Help for water resource conservation

A)Land and Building Details:

A) Land

  1. approx 100 Ropani at Dana s/s
  2. approx  150 Ropani at Kushma s/s
  3. approx 250 Ropani at New Butwal s/s
  4. approx 50 Ropani for Dana Kushma Transmission Line

 

CONTACT US

NEPAL ELECTRICITY AUTHORITY

(PROJECT MANAGEMENT DIRECTORATE)

Matatirtha, Kathmandu Nepal
Tel: +977-1-4785216
Fax: +977-1-4785217
Email: info@nea.org.np