Distribution System Augmentation and Expansion Project

  1. Project Detail/Scope: Construction of 25 New 33/11kV Substations and its associated 33kV, 11kV and 400V Lines
  2. Project Objective and Goals: Enhance the Distribution Capacity and Improve Energy Efficiency with improved quality of supply and energy access.
  3. Contract Packages:
    1. Contract Package: LOT 1
      1. Contract No: ICB-PMD-DSAEP-071/72-04, Lot 1: Expansion of Distribution Networks in Eastern Region of Nepal
      2. Scope of Work: Lot 1 (Construction of 13 Nos. New 33/11kV S/S (3MVA & 6MVA) at Makwanpur, Parsa, Rautahat, Khotang, Saptari, Bhojpur, Terathum, Morang, Jhapa, Illam Districts and construction of associated 33kV, 11kV and 0.4kV Lines)
      3. IFB Publication Date: 07 January 2016
      4. Contract Agreement Date: 15 June 2016
      5. Contract Effective Date: 24 August 2016
      6. Contract Completion Date: 24 August 2018
      7. Cost of Contract: USD 6,262,037.50 + NPR 734,927,619.44
    2. Contract Package: LOT 2
      1. Contract No: ICB-PMD-DSAEP-072/73-01, Lot 2: Expansion of Distribution Networks in Western Region of Nepal
      2. Scope of Work: Lot 2 (Construction of 12 Nos. New 33/11kV S/S (3MVA & 6MVA) at Gorkha, Tanahu, Myagdi, Nawalparasi, Rupandehi, Kapilbastu, Palpa, Arghakhachi, Rolpa, Kailali, Doti Districts and construction of associated 33kV, 11kV and 0.4kV Lines)
      3. IFB Publication Date: 07 January 2016
      4. Contract Agreement Date: 16 July 2016
      5. Contract Effective Date: 02 September 2016
  1. Contract Completion Date: 02 September 2018
  2. Cost of Contract: USD 6,815,957.62 + NPR 721,087,740.13
  3. Contract Package: LOT 3
    1. Contract No: ICB-PMD-DSAEP-071/72-01, Lot 3: Distribution Network Improvement
    2. Scope of Work: Lot 3 (Upgradation of 11 Nos. 33/11kV S/S (3MVA & 6MVA) at Dhangadi, Nepalgunj, Butwal Chauraha, Bhairahawa, Sindhuli, Bisanpur, Aurahi, Haripur, Khanar, Rangeli, Fikkal and construction of associated 33kV, 11kV and 0.4kV Lines)
    3. IFB Publication Date: 11 June 2015
    4. Contract Agreement Date: 22 February 2016
    5. Contract Effective Date: 15 June 2016
    6. Contract Completion Date: 15 June 2018
    7. Cost of Contract: USD 13,767,032.41 + NPR 134,194,801.88
  1. Progress:
    1. Physical: 61.96%
    2. Financial: 55.88%
  2. Disbursement Target of the Year: NPR 2,000,000,000
  3. Disbursement Amount of the Year: NPR 975,390,342.34
  4. Hindrance of the Projects:
  5. Efforts to Mitigate Hindrance:
  6. Budget for F/Y 2017/18 (2074/74)
    1. Nepal Government: NPR 170,000,000
    2. Asian Development: NPR 2,000,000,000
  7. Target of Expenses for F/Y 2017/2018:
  8. Social and Environmental Activities including GESI and their impacts to society:
  9. Land and Building Details: Land required for all the new Substation Construction were acquired till last Fiscal Year.

 