Government of Nepal (GON) has received Loan No. 3139-NEP from the Asian Development Bank and Grant 0397 from the Government of Norway towards the cost of SASEC Power System Expansion Project.
Contract Package 1 (Grid Substation Reinforcement Project):
The main components of the "Grid Substation Reinforcement Project" include expansion / up-gradation of Various Grid Substations and Power House Switchyard. The up gradation and reinforcement works are to be performed at following substations:
GANDAK S/S EXPANSION Gandak substation is the switchyard of the Gandak Power Plant. The scope intends to add following equipment and construction of new control building. The expanded substation shall be unmanned substation, controlled, monitored from existing Gandak Control Room. The substation is to be developed from new land near to the existing switchyard.
General scope in this substation includes
BUTWAL S/S BAY EXTENSION
General scope in this substation includes
BHARATPUR SUBSTATION EXTENSION
General scope in this substation includes
BANEPA S/S UPGRADATION General scope in this substation includes
DAMAULI S/S UPGRADATION
General scope in this substation includes
LAHAN S/S UPGRADATION General scope in this substation includes
DHALKEBAR S/S UPGRADATION
General scope in this substation includes
NEW KAWASOTI S/S UPGRADATION
General scope in this substation includes
Contract Package 2 (Design, Supply, Installation and Commissioning of Dhalkebar - Mujeliya 33kV Line Upgrading Project):
This project covers the execution of Upgradation of 33 kV Double Circuit Dhalkebar –Mujeliya Sub-Transmission Line (HTLS Conductor) with restoration of towers and installation of Two (2) 33 kV, 10 MVar Capacitor Banks at Mujeliya Substation.
|
Contract Package 1 (Grid Substation Reinforcement Project) : The main objective of the Project is Upgradation of Substation Capacity of various substation to improve reliability and the quality of the system and to cater growing load of the country.
Contract Package 2 (Design, Supply, Installation and Commissioning of Dhalkebar - Mujeliya 33kV Line Upgrading Project):
The main objective of the Project is Upgradation of 33 kV Dhalkebar –Mujeliya Line to increase the Capacity of the Line to improve reliability and the quality of the system and to cater growing load of the Janakpur Area.
|
IFB Publication Date: 24/11/2104
Contract Agreement Date: 05/07/2015
Contract Effective Date: 01/11/2015
Original Contract Completion Date: 21/07/2017
Revised Contract Completion Date: 29/12/2017
Cost of Contract: USD 3,687,101.76, INR. 79,733,918.74 & NRs. 134,643,028.14 (Original Contract Amount) Variation 1: USD 32,688.00, INR. 6,862,140.98 & NRs. 1,124,142.62 Variation 2: NRs. 2,017,545.52
Revised Cost of Contract: USD 3,719,789.76, INR. 85,820,772.10 & NRs. 137,742,447.87
Major Activities: Project Completed
Contract Package 2 (Design, Supply, Installation and Commissioning of Dhalkebar - Mujeliya 33kV Line Upgrading Project):
IFB Publication Date: 07/02/2018
Bid Opening Date: 21/03/2018
Contract Agreement Date:
Contract Completion Date: 15 Months from Contract Effective Date
Cost of Contract: USD 2,962,101.41 (Estimated)
Major Activities: Technical Bid Under Evaluation.
Financial Evaluation Report submitted to ADB for concurrence: Not Forwarded
|
|
|
|
|
|
Nepal Government: NRs. 15.9 Million ADB: NRs. 120 Million
|
Advance Payment, Mobilization and Supply of some equipment for Contract No 2.
|
|
|